<Systems Summary

The systems below were developed with varying amounts of customer involvement. In all cases, S3 provided the technical capability to see the system through to production and beyond.


SCADA Systems

CLIENT: SOUTH JERSEY GAS
Project: Install and support total SCADA system in 1999.
Rapid SCADA used in conjunction with Intellution Dynamics.
Primarily SJG developed and maintained.
Project: LNG Vaporizers - Automation of 3 BS&B direct fired vaporizers
(improved startup), ESD and flow calculations with Bristol Babcock
RTU's

CLIENT: KEYSPAN ENERGY DELIVERY
Project: Install and support total SCADA system in 2000 for Massachusetts
(Colonial Gas) expansion territories.  Rapid SCADA used in conjunction with
Intellution Dynamics and hot standby redundancy. Turnkey
Project: Complete software standardization for all RTU's and incorporation into
Rapid SCADA for New Hampshire (Energy North). Turnkey

CLIENT: SOUTHERN CONNECTICUT GAS COMPANY
Project: Install and support total SCADA system in 1999.
Rapid SCADA used in conjunction with Intellution Dynamics.
Primarily SCG developed and maintained.
Project: Install multiple SCADA Transfer Gate Stations implementing
RTU's with Communication planning.
Project: Develop and implement software for over 300 Digital
transmitters.

CLIENT: NEW ENGLAND GAS
Project: Install and support total SCADA system in 2000.
Rapid SCADA used in conjunction with Intellution Dynamics.
Turnkey

CLIENT: CONNECTICUT NATURAL GAS COMPANY
Project: Install and support total SCADA system in 2002.
Rapid SCADA used in conjunction with Intellution Dynamics.
Primarily CNG developed and maintained.
Project: Phased approach planning for Disaster Recovery.

CLIENT: BAY STATE GAS COMPANY
Project: Complete automation of LP/LNG plants. Distributed SCADA
system with 50 RTU's and backup MMI system. Complete T1 WAN
implementation and DDS network consultation.
Project: Monson-Palmer Pipeline: Complete RTU software implementation
for logic controlling transmission pipe blowdown. Utilization of
feedback from Farmer Associates Pressure Point Analysis System.


General Business Systems

CLIENT: FALL RIVER GAS COMPANY

Project: 50 User Client/Server SQL database system for Customer Relationship Management, Service Work Order, Job Tracking and Meter Inventory. System integrated with Billing Mainframe Computer.  Features including service job scheduling and optimization, and meter life cycle.  Reporting included Customer History, Job Tracking, Meter Tracking, State Meter Reports and etc.  WAN installation and consulting.
Project: System expansion with Equimeter Corrector instrument communication and data retrieval for interruptible/firm customers.
Project: System expansion for Supplier Management per Deregulation and State Collaborative requirements.  Nomination and final billing with penalty assessment and historical volume data storage.


Control Systems for LNG/LP Facilities

CLIENT: BAY STATE GAS COMPANY
Project: Lawrence LP Plant - Total software process automation with
Bristol Babcock RTU. MMI incorporation, Compressor control, electronic
and process consulting.
Project: Easton LNG Plant - Plant Monitoring and flow calculation with
Bristol Babcock RTU.
Project: Brockton LP Plant - Total software process automation with
Bristol Babcock RTU. MMI incorporation, Compressor control, and process
consulting.
Project: Taunton LP Plant - Total software process automation with
Bristol Babcock RTU. Complete Compressors control, electronic and
process consulting.
Project: Medway LP Plant - Total software process automation with
Bristol Babcock RTU. Complete Compressors control, electronic and
process consulting.
Project: Ludlow LNG Plant - Plant Monitoring w/ESD and flow calculation
with Bristol Babcock RTU.
Project: East Longmeadow LP Plant - Total software process automation
with Bristol Babcock RTU. Complete Compressors control,
electronic and process consulting.
Project: North Hampton LP Plant - Total software process automation
with Bristol Babcock RTU. Complete Compressors control, electronic
and process consulting.

CLIENT: KEYSPAN ENERGY DELIVERY
Project: South Yarmouth LNG Plant - Total software process automation
with Bristol Babcock RTU. MMI incorporation, electronic and process
consulting.
Project: Tewksbury LNG Plant - Total software process automation for
Stabilization with Bristol Babcock RTU.  MMI incorporation, electronic
and process consulting. Short Haul Communications.
Project: Haverhill LNG Plant - 100 Point Plant Monitoring w/ESD and
flow calculation using Bristol Babcock RTU. MMI incorporation, electronic
and process consulting. Mass. DPU approved for unattendance
while not vaporizing.

CLIENT: NORTHERN UTILITIES
Project: Lewiston ME LNG Plant - Total software process automation with
Bristol Babcock RTU. HMI incorporation, electronic and process consulting.
DOT approved.
Project: Portland ME LP Plant - Total software process automation with
Bristol Babcock RTU. Compressor control, electronic and process
consulting.